The Rajdhani Unnayan Kartripakkha (RAJUK) has yet to take visible enforcement action against a 10-storey residential building on RK Mission Road in the capital, despite identifying 11 deviations from its approved design and issuing a final notice nearly two years ago.
The building, named MAM Kingdom, is located at holding numbers 6/1 and 6/2 on RK Mission Road under Wari Police Station. RAJUK’s Zone 6/1 issued a notice on February 10, 2025, directing the owners to remove the unauthorised portions within seven days.
The notice warned that legal action would follow if the violations were not removed within the stipulated period. However, no visible eviction or removal operation has taken place so far, while the developer, Total Real Estate Limited, has nearly completed construction and reportedly begun handing over apartment keys to some buyers.
According to available documents, RAJUK approved construction of a 10-storey residential building with one basement on November 12, 2009, following an application by the landowners, Md Ahmad Arefin Talukder and others. The approval bears memorandum number RAJUK/NAA/3C-4-0521/09/723. Total Real Estate Limited is the developer responsible for the project.
Despite receiving approval nearly 17 years ago, the developer has yet to complete the handover of apartments to all buyers, according to complaints from landowners and flat purchasers. Delays in construction and alleged deviations from the approved plan have added to their difficulties. Although keys have reportedly been handed over for a few apartments, many buyers remain uncertain about when they will be able to take possession after investing substantial amounts of money over the years.
The RAJUK notice identified 11 types of deviations, including failure to maintain the required space for a rear road, reducing the width of a staircase, extending balconies and slabs beyond the approved design, reducing designated open spaces and constructing additional rooms on the rooftop.
According to the notice, the approved plan required the developer to leave a space measuring 1.79 metres by 7.21 metres for the road at the rear of the building. However, the required space was not maintained.
The approved width of the staircase on the right side of the building was 1.15 metres, but an inspection found it to be only 0.63 metres.
The notice also stated that three balconies measuring 1.80 metres by 1.22 metres each had been added to the front of the building beyond the approved design. Another balcony, measuring 1.50 metres by 6.70 metres, was allegedly extended on the left side.
In addition, a continuous slab measuring approximately 1.14 metres was extended on the left side of the building beyond the approved plan. Similar extensions were found on the right side, measuring approximately 1.60 metres, and at the rear, measuring 0.67 metres by 3.04 metres.
Discrepancies were also identified in the designated open space on the left side of the building. The approved plan provided for a void or open space measuring approximately 2.50 metres by 2.60 metres in the middle of the building. However, an inspection found the space to be only 1.80 metres by 1.16 metres.
The rooftop construction also came under scrutiny. According to the notice, a gym room measuring 7.39 metres by 9.60 metres and a community room measuring 5.33 metres by 10.05 metres had been built without approval under the sanctioned design.
The alleged violations were identified following an on-site inspection conducted by RAJUK officials before the notice was issued on February 10, 2025.
Between 2009 and 2025, at least six to seven building inspectors and five authorised officers served in the relevant RAJUK zone. Questions have therefore been raised over why the alleged irregularities were not detected earlier during the construction period.
Despite the notice, construction has progressed and the developer has reportedly started handing over apartment keys. The lack of visible enforcement has also raised questions about RAJUK’s monitoring and implementation of building regulations.
When contacted about the MAM Kingdom building, Abdullah Al Mamun, authorised officer of the relevant RAJUK zone said, “The matter is under consideration. An eviction drive will be conducted in the area at any time.”
However, no further explanation was available regarding the delay in enforcement action following the notice. The developer, Total Real Estate Limited, could not be reached for comment for this report.
The difficulties faced by the landowners and apartment buyers, along with their complaints, will be examined in a subsequent report.